India's First Bullet Train Makes Steady Progress: NHSRCL Update
India's Mumbai-Ahmedabad high-speed rail project reports significant advancements, with viaducts, piers, and tunnels nearing completion. The NHSRCL highlights progress in electrification, noise barriers, and key station infrastructure. As milestones are reached, the project moves closer to unveiling India's first bullet train corridor.
- Country:
- India
India's ambitious project to connect Mumbai and Ahmedabad via a high-speed rail corridor is advancing significantly, as revealed by the National High Speed Rail Corporation Limited (NHSRCL). As of March 29, 2026, 343 kilometers of viaduct and 434 kilometers of pier constructions are complete out of the total 508-kilometer alignment.
The NHSRCL reports notable progress in key structural developments, including bridge works with 17 river bridges, 5 prestressed concrete, and 13 steel bridges finished. Safety infrastructure has been prioritized with over 5.6 lakh noise barriers installed along 280 kilometers of the route.
Track and electrification efforts are also making strides, with 360 track kilometers of reinforced concrete tracks completed and more than 6,900 overhead electrification masts installed. In Maharashtra, critical advancements in tunnel construction have been achieved, including a breakthrough in two mountain tunnels and excavation in progress for a major underground tunnel.