Vande Bharat Trains Off Track: Technical Oversight Causes Major Delays
Two Vande Bharat superfast trains scheduled between Sabarmati and Gurgaon were unable to run due to technical incompatibility with the route's overhead equipment. The trains were diverted, causing significant delays. Officials have been criticized for planning oversights but have not commented on potential actions or accountability measures.
- Country:
- India
The Vande Bharat Superfast trains, designed to swiftly connect Sabarmati and Gurgaon, encountered an unexpected setback on October 5 and 6, failing to operate as scheduled. The trains, operated by the Ahmedabad Division of Western Railways, could not run the intended routes due to technical incompatibility with the height of the overhead equipment.
Officials revealed that the existing trainsets were equipped with pantographs suitable for 5-metre wires, while the route featured 7.3-metre high overhead lines. This misalignment necessitated unexpected diversions, extending travel times from 14 hours and 55 minutes to as much as 28 hours, prompting criticism over planning lapses.
Despite media reports highlighting the chaos and inconvenience faced by passengers, Ved Prakash, Divisional Railway Manager, remained silent on whether any remedial actions would be initiated against the accountable departments for this oversight. The incident underscores an urgent need for improved coordination and planning within railway operations.
ALSO READ
-
Connecting Kashmir: Vande Bharat Trains Transforming Rail Travel
-
Textile Hubs to Benefit from Vande Bharat Train Halts
-
Vande Bharat Express: New Stop at Reasi to Boost Connectivity
-
Case registered after video of fight between pantry staff on Vande Bharat Express goes viral
-
First Vande Bharat sleeper train to roll out next year, production to begin by December: KINET Project Director